Project Case Study

Services Australia – Centrelink Box Hill

Melbourne Energy Group was engaged to design, supply, install and commission a rooftop solar PV system for the Services Australia Centrelink office in Box Hill.

The objective was to deliver a high-quality commercial solar installation that would reduce grid electricity consumption while meeting the operational requirements of an active government facility.

The project required careful planning due to the site’s location within a busy metropolitan environment, where uninterrupted public access and day-to-day operations were essential throughout construction.

55.0kW

Nominal DC Power

1 × Sungrow SG50CX-P2 50kW three-phase inverter

Inverter

88 × JA Solar 625W bifacial solar modules

Modules

melbourne-energy-group-case-study-centerlink-boxhill1

melbourne-energy-group-case-study-centerlink-boxhill1

Project Requirements

The project scope included:

  • Design and engineering of a commercial rooftop solar system
  • Procurement and Supply of all solar equipment and components
  • Installation of the complete PV system
  • Electrical integration
  • Metering and monitoring
  • Testing and commissioning of the solar PV system

The installed system comprised:

  • 88 × JA Solar 625W bifacial solar modules
  • 1 × Sungrow SG50CX-P2 50kW three-phase inverter
  • Roof-mounted racking system
  • Integrated monitoring platform

The final design delivers a DC capacity of 55.0 kW with a 50.0 kW AC inverter, optimised to maximise annual energy production from the available roof space.

Project Delivery Highlights

  • A government solar project delivered while remaining operational
  • Installation completed within a five-day construction window
  • Noise restrictions successfully managed through construction scheduling
  • Public safety maintained throughout installation
  • High-quality rooftop installation integrated into an existing commercial building

Project Delivery

The Centrelink Box Hill project was delivered within a fully operational government facility, requiring construction activities to be carefully coordinated around the site’s daily operations. Maintaining business continuity, public safety and building accessibility was a primary consideration throughout the project.
Project delivery was influenced by several operational constraints, including:

  • Strict daytime noise restrictions that limited the use of conventional installation equipment.
  • Continuous public access requirements, with the facility remaining open throughout the construction period.
  • High pedestrian traffic surrounding the building, requiring controlled work zones and clearly defined exclusion areas.
  • Restricted site access, limiting material handling, equipment movement and rooftop logistics.
  • The need to maintain normal building operations without disrupting staff or public services.

To address these challenges, Melbourne Energy Group developed a detailed construction methodology prior to commencing works. Activities generating elevated noise were scheduled outside standard operating hours, while specialised low-noise equipment was utilised wherever practical to minimise disruption.

Material deliveries, rooftop access and installation sequencing were carefully coordinated to maximise productivity within the available work windows.

Comprehensive site safety planning, pedestrian management and communication protocols were implemented throughout the project to ensure the safe movement of contractors, building occupants and members of the public.

Despite the operational complexity of the site, the complete installation was successfully delivered within a five-day on-site construction program.

The successful delivery of this project demonstrates Melbourne Energy Group’s capability to execute commercial solar installations within complex operational environments where safety, stakeholder coordination and programme management are critical to project success.

Melbourne Energy’s Group Capabilities

Government buildings can present unique delivery challenges that extend past the technical requirement of installing solar infrastructure. Operational continuity, public safety, restricted access and stakeholder coordination are critical considerations that require experienced project management.

The Services Australia Centrelink Box Hill project demonstrates Melbourne Energy Group’s capability to successfully deliver commercial solar projects within complex operational environments while maintaining safety, quality and programme outcomes.

System Performance

The completed system is modelled to generate approximately:

  • 55.0 kW DC installed capacity
  • 50.0 kW AC inverter capacity
  • 66.22 MWh annual electricity production
  • 1,204 kWh per installed kW annually
  • 76.1% Performance Ratio

These performance figures were modelled using Meteonorm weather data through the HelioScope design platform.

Project Outcomes

The completed installation provides Services Australia with long-term renewable energy generation while making productive use of existing rooftop infrastructure.
Expected outcomes include:

  • Reduced reliance on grid electricity during daylight operating hours
  • Lower long-term electricity costs
  • Improved utilisation of available roof space
  • Reduced operational carbon emissions
  • Modern monitoring capability for ongoing system performance

Key Project Metrics

Metric Result
Client Services Australia – Centrelink Box Hill
Location Box Hill, Victoria
System Size 55.0 kW DC
Inverter Capacity 50.0 kW AC
Solar Panels 88 × JA Solar 625W
Inverter Sungrow SG50CX-P2
Estimated Annual Generation 66.22 MWh
Performance Ratio 76.1%
Installation Duration 5 Days

Discuss Your Solar Project with Melbourne Energy Group

Melbourne Energy Group partners with government, councils and community organisations to design and implement renewable energy systems that reduce operating costs.

To assess your venue’s opportunity we provide:
• Energy usage analysis
• System design and financial modelling
• Comparison of purchase, finance and PPA options
• Installation timeline and operational transition plan

To begin, request an energy assessment with Melbourne Energy Group.