Workplace EV Charging for Business Fleets
Learn how to plan workplace EV charging infrastructure for Australian businesses. Understand AC and DC charging, fleet planning, electrical infrastructure, load management, and integrating EV charging with commercial solar and battery storage.
A Guide to Planning Commercial EV Charging Infrastructure
Introduction
As more Australian businesses transition company vehicles to electric vehicles (EVs), workplace charging is becoming an increasingly important part of commercial building infrastructure.
Whether operating a small fleet of service vehicles, managing a growing commercial fleet or supporting high-utilisation vehicles that require rapid turnaround, installing the right charging infrastructure can improve operational efficiency while preparing a business for future fleet growth.
Unlike residential charging, commercial EV charging requires consideration of fleet operations, vehicle movements, charging windows, electrical capacity, charger selection and future expansion.
For many businesses, AC workplace charging provides an effective solution where vehicles remain parked for extended periods. Others may require DC fast charging to minimise downtime and return vehicles to operation more quickly. In some cases, a combination of AC and DC charging delivers the greatest operational flexibility.
Understanding these requirements early helps businesses design charging infrastructure that supports current operational needs while allowing for future growth.
Key Takeaways
| Topic | Summary |
|---|---|
| Best suited for | Businesses operating two or more electric vehicles |
| Typical charging solutions | AC workplace chargers (7kW–22kW) and DC fast chargers where operational requirements demand rapid vehicle turnaround |
| Common installation locations | Depots, offices, workshops, warehouses, vehicle holding yards staff and commercial car parks |
| Planning considerations | Fleet growth, electrical capacity, parking layout, charging requirements and energy management |
| Can integrate with | Commercial solar, battery storage and energy monitoring |
Australian EV Fleet Market Snapshot
| Industry Indicator | Current Position |
|---|---|
| EV adoption | Increasing across residential and commercial markets |
| Fleet electrification | Growing across trades, healthcare, councils, logistics, service industries and commercial fleets |
| Workplace charging | Becoming standard infrastructure for depot-based and commercial fleets |
| Typical commercial charging | AC workplace charging for parked vehicles, with DC fast charging increasingly adopted by businesses requiring rapid vehicle turnaround |
| Long-term trend | Integration of EV charging with commercial solar, battery storage and intelligent energy management systems |
Who Is This Guide For?
This guide is intended for organisations planning or expanding workplace EV charging infrastructure, including:
- Property maintenance companies
- Building and facility managers
- Healthcare providers
- Local government
- Logistics and delivery operators
- Sales and service organisations
- Trades businesses
- Commercial fleet operators
- Businesses transitioning company vehicles to EVs
Why Businesses Are Installing Workplace EV Charging
As Australian businesses continue to electrify their fleets, workplace EV charging is becoming an increasingly important part of commercial infrastructure.
Charging vehicles while they are parked at a workplace or depot can improve operational efficiency and reduce reliance on public charging infrastructure.
The appropriate charging solution depends on how vehicles are used.
AC workplace charging is often suitable where vehicles remain parked for extended periods, while DC fast charging is better suited to high-utilisation fleets or operations requiring rapid vehicle turnaround.
Many businesses implement a combination of AC and DC charging to support different vehicle types and operational requirements.
For many organisations, workplace EV charging also supports:
- Fleet transition planning
- Reduced reliance on public charging infrastructure
- Improved operational efficiency
- Sustainability objectives
- Integration with commercial solar and battery storage
- Future fleet expansion
- Long-term energy management strategies
Which Businesses Are Installing Workplace Charging?
Workplace EV charging is being adopted across a broad range of industries as organisations transition fleet vehicles to electric transport.
| Industry | Typical Fleet Size | Typical Charging Requirement |
|---|---|---|
| Electrical Contractors | 2–20 vehicles | AC workplace charging |
| Plumbing & HVAC | 2–30 vehicles | AC workplace charging |
| Property Maintenance | 5–50 vehicles | Daily return-to-base charging |
| Healthcare | 2–20 vehicles | AC charging with potential DC fast charging for high-utilisation fleets |
| Local Government | Pool vehicles and utilities | Mixed AC charging with DC charging where operational requirements demand |
| Logistics & Delivery | 5–50 vehicles | Mixed AC and DC fleet charging |
| Sales & Service | 2–15 vehicles | Workplace charging |
| Vehicle Distribution | Large commercial fleets | Mixed AC and DC charging with fast turnaround capability |
The appropriate charging solution varies depending on fleet size, vehicle utilisation and operational requirements.
Planning Workplace EV Charging Infrastructure
Vehicle usage, operating hours, electricity demand, charging windows and future fleet growth all influence how workplace charging infrastructure should be designed.
The appropriate EV charging infrastructure requires consideration of fleet operations, vehicle utilisation and business requirements, this will assess the required charging speed options.
An assessment considers the following.
Fleet Operations
Understanding how a fleet operates is the first step in planning workplace EV charging infrastructure.
A typical assessment considers:
- Fleet size
- Daily travel distances
- Vehicle return times
- Operating hours
- Time available for charging
- Planned fleet expansion
This information helps determine the operational requirements of the charging infrastructure and provides the basis for charger selection, electrical design and future expansion planning.
Vehicle Charging Requirements
Vehicle charging requirements are determined by how the fleet operates and the amount of time available to recharge vehicles.
An assessment reviews:
- Battery capacities
- Daily energy requirements
- Vehicle downtime
- Charging frequency
- Required vehicle turnaround times
Small and medium-sized fleets, AC charging provides sufficient charging while vehicles remain parked during business hours or overnight.
Businesses with higher vehicle utilisation, limited charging windows or rapid turnaround requirements may benefit from DC fast charging.
Electrical Infrastructure
Melbourne Energy Group’s technical team inspect the site’s electrical capacity and determine if the existing infrastructure can support the proposed charging system.
Assessments include:
- Main switchboard capacity
- Existing electrical demand
- Available electrical supply
- Distribution boards
- Sub-main capacity
- Future electrical requirements
Infrastructure upgrades can be incorporated into the project to support additional charging capacity and allow for future expansion.
Projects incorporating DC fast charging can require higher-capacity electrical infrastructure due to the increased power demand of fast charging equipment.
Site Layout
The site layout helps determine how the EV charging infrastructure can be installed safely, efficiently and with minimal disruption to normal business operations.
A site assessment typically considers:
- Parking arrangements
- Vehicle movements
- Charger accessibility
- Cable routes
- Switchboard locations
- Traffic movements
- Future charger locations
Understanding these site conditions helps identify suitable charger locations, optimise cable routes, support safe vehicle access and allow for future expansion where required.
Future Fleet Growth
Fleet electrification is often implemented progressively as vehicles are replaced or operational requirements change.
Planning for expansion during the initial installation can reduce future construction works, minimise disruption to business operations and avoid unnecessary upgrades as charging demand increases.

Workplace EV Charging for Business Fleets
Choosing the Right Workplace Charger
The most appropriate EV charging solution depends on fleet operations, vehicle utilisation and the time available for charging.
| Charger Type | Typical Application |
|---|---|
| 7kW AC | Overnight workplace charging |
| 11kW AC | Mixed workplace charging |
| 22kW AC | Daily fleet charging where vehicles remain parked for extended periods |
| 30–60kW DC Fast Charger | Fleets requiring faster charging during operational hours |
| 120kW+ DC Fast Charger | High-utilisation fleets, logistics operations, vehicle distribution facilities and commercial sites requiring rapid vehicle turnaround |
AC charging provides sufficient capacity where vehicles remain parked for extended periods. Businesses with high-utilisation fleets or vehicles requiring rapid turnaround may benefit from DC fast charging.
Commercial sites utilise a combination of AC and DC charging to support different operational requirements while balancing charging performance and infrastructure investment.
Managing Charging Demand
Charging multiple vehicles at the same time increases electricity demand and influences the design of the electrical infrastructure.
A load management system distributes available electrical capacity across multiple chargers, enabling vehicles to charge without exceeding the site’s available electrical supply. This can reduce the need for unnecessary electrical infrastructure upgrades while providing capacity for future fleet expansion.
DC fast charging places higher demand on the electrical network than AC workplace charging. Projects incorporating DC chargers require an assessment of electrical capacity, site demand and charger utilisation to determine whether load management, staged charging or electrical infrastructure upgrades form part of the system design.
Managing charging demand during the planning stage ensures the charging infrastructure aligns with the site’s electrical capacity and operational requirements.
Integrating Workplace Charging with Solar and Battery Storage
Commercial solar, battery storage and EV charging can be designed as a single energy system.
Solar generation offsets electricity used for daytime vehicle charging, increasing onsite energy utilisation and reducing grid electricity consumption.
Battery storage stores excess solar generation for use during periods of higher electricity demand or when solar generation is unavailable. On sites incorporating DC fast charging, battery storage can also reduce peak grid demand by supplying stored energy during high charging periods.
Assessing EV charging, commercial solar and battery storage as part of the same project informs system design, electrical infrastructure requirements and long-term energy management.
Commercial Planning Considerations
Planning a workplace EV charging project involves assessing the operational, electrical and site requirements that influence system design.
| Consideration | Outcome |
|---|---|
| Fleet size | Determines charging capacity requirements |
| Vehicle usage | Influences charger selection and charging schedules |
| Charging speed requirements | Determines whether AC charging, DC fast charging or a combination of both is appropriate |
| Electrical capacity | Determines whether infrastructure upgrades are required |
| Parking layout | Influences charger locations |
| Future fleet growth | Allows infrastructure to expand over time |
| Solar integration | Supports onsite renewable energy use |
| Battery storage | Provides additional charging flexibility |
| Energy monitoring | Supports operational visibility |
Workplace EV Charging Planning Checklist
| Assessment Item | ✓ |
|---|---|
| Review current fleet size | ☐ |
| Forecast future fleet growth | ☐ |
| Assess vehicle operating hours | ☐ |
| Assess daily vehicle turnaround requirements | ☐ |
| Determine whether AC charging, DC fast charging or a combination of both best suits operational requirements | ☐ |
| Review parking layout | ☐ |
| Assess electrical capacity | ☐ |
| Review main switchboard capacity | ☐ |
| Assess electrical infrastructure for high-powered chargers where applicable | ☐ |
| Review load management requirements | ☐ |
| Consider commercial solar integration | ☐ |
| Consider battery storage | ☐ |
| Plan for future charger expansion | ☐ |
Workplace EV Charging Case Study

Commercial EV Charging Infrastructure
Project Snapshot
Industry: Electric Vehicle Manufacturing & Distribution
Location: Derrimut, Victoria
Project Type: Commercial EV Charging Infrastructure
Project Duration: 14 Days
Project Overview
A national electric vehicle manufacturer required a large-scale workplace charging solution for a new vehicle holding and pre-delivery facility in Melbourne’s west designed to accommodate more than 2,000 vehicles.
To support vehicle preparation and dispatch operations, the facility required charging infrastructure capable of safely and efficiently charging multiple vehicles each day before distribution to dealerships.
The project also carried a fixed completion deadline, with the charging network required to be fully operational before the first shipment of vehicles arrived on site.
Project Requirements
The charging infrastructure needed to:
- Support both AC and DC fleet charging
- Deliver high-capacity fast charging for rapid vehicle turnaround
- Integrate with the site’s electrical and fire safety systems
- Be installed alongside multiple contractors working across the facility
- Be fully commissioned within a 14-day construction program
The project also required substantial electrical infrastructure capable of supporting multiple high-powered DC fast chargers.
Charging Infrastructure Installed
To meet the operational requirements of the site, Melbourne Energy Group delivered:
- 2 × Schneider Electric DC Pro 120kW Fast Chargers
- 1 × Schneider Electric DC Pro 60kW Fast Charger
- 9 × Schneider Electric AC Pro Single-Phase Chargers
The combination of AC and DC charging allows the facility to support both routine vehicle charging and rapid charging where operational requirements demand fast vehicle turnaround.
Electrical Works Completed
The project included:
- Heavy-duty sub-main installations for DC charging equipment
- Commercial electrical distribution infrastructure
- Cable containment throughout the charging network
- Charger installation and commissioning
- Integration with the site’s fire alarm system
- Emergency Power Off (EPO) installation for charging network isolation
The completed installation provides a safe, reliable charging network capable of supporting high-volume commercial fleet operations.
Installation Considerations
The project was delivered within an active construction environment alongside multiple contractors.
Key delivery considerations included:
- Maintaining progress within a fixed 14-day construction program
- Coordinating installation activities with concurrent civil and line-marking works
- Installing heavy-duty electrical infrastructure for DC fast charging
- Integrating life safety systems without disrupting other site activities
Through careful planning and coordination, the charging infrastructure was commissioned within the required project timeframe.
Project Outcomes
The completed charging network provides infrastructure capable of supporting daily vehicle charging operations prior to vehicle distribution.
Project outcomes included:
- Commercial EV charging infrastructure delivered on schedule
- Combined AC and DC charging capability
- Integrated electrical and fire safety systems
- Infrastructure designed for high-volume vehicle processing
- Charging network operational prior to vehicle deliveries
Key Project Metrics
| Metric | Outcome |
|---|---|
| Project Duration | 14 Days |
| DC Fast Chargers | 3 Units (120kW & 60kW) |
| AC Chargers | 9 Units |
| Safety Integration | Fire Alarm & Emergency Power Off (EPO) |
| Electrical Infrastructure | Heavy-duty sub-mains and commercial distribution network |
| Delivery Performance | Completed and commissioned on schedule |
Frequently Asked Questions
How many EV chargers does my business need?
The number of chargers is determined by fleet size, vehicle usage, operating hours, daily energy requirements and the time available for charging. A fleet assessment informs the number, type and location of chargers required to support current operations and future fleet expansion.
What size EV charger is suitable for a commercial fleet?
Charger selection is determined by fleet operations and charging requirements. AC charging suits vehicles parked for extended periods, while DC fast charging is designed for fleets requiring rapid vehicle turnaround or continuous operation.
When is DC fast charging appropriate?
DC fast charging suits fleets with high vehicle utilisation, multiple operating shifts or limited charging windows. Logistics operators, vehicle distribution centres, service fleets and commercial transport businesses are common applications.
Can AC and DC chargers be installed on the same site?
Yes. AC and DC charging infrastructure is frequently installed together to support different vehicle types and operating requirements. AC chargers provide routine workplace charging, while DC chargers reduce charging time for vehicles returning to service throughout the day.
Can EV chargers be installed at an existing workplace?
Yes. Existing electrical infrastructure is assessed to determine whether the available electrical capacity supports the proposed charging infrastructure or whether electrical upgrades form part of the project.
Does DC fast charging require additional electrical infrastructure?
DC fast chargers have higher electrical demand than AC chargers. Project requirements are determined by charger capacity, the number of chargers being installed and the site’s existing electrical infrastructure. This assessment may include switchboards, sub-mains, network capacity and load management.
Can workplace EV charging integrate with commercial solar?
Yes. Commercial solar offsets electricity used for daytime vehicle charging, reducing grid electricity consumption and increasing onsite utilisation of renewable energy.
What role does battery storage play in workplace EV charging?
Battery storage stores excess solar generation for later use and supplies energy during periods of high charging demand. It also reduces peak grid demand on sites incorporating DC fast charging.
Can charging infrastructure be expanded as fleet requirements change?
Yes. Future fleet growth forms part of the initial planning process. Considering future electrical capacity and charger locations during system design simplifies expansion and reduces future construction works.
Next Steps
A workplace EV charging assessment typically includes:
- Reviewing fleet operations
- Assessing vehicle charging requirements
- Inspecting existing electrical infrastructure
- Determining whether AC charging, DC fast charging or a combination of both best suits operational requirements
- Selecting suitable charging equipment
- Planning charger locations
- Reviewing load management requirements
- Assessing opportunities to integrate commercial solar and battery storage
- Allowing for future fleet expansion
Understanding these requirements early helps organisations develop workplace EV charging infrastructure that supports both current operational needs and future fleet growth.
Discuss Your Workplace EV Charging Project with Melbourne Energy Group
Melbourne Energy Group works with businesses, councils and community organisations to assess workplace EV charging requirements and design commercial charging infrastructure that integrates with existing electrical systems, commercial solar and battery storage where appropriate.
Our team provides advice on:
- AC workplace charging
- DC fast charging
- Fleet charging infrastructure
- Electrical infrastructure upgrades
- Load management
- Commercial solar integration
- Battery energy storage
- Future fleet expansion
Melbourne Energy Group designs and delivers commercial EV charging, solar and battery storage systems that integrate with existing electrical infrastructure and support long-term operational requirements.
Reference Sources
| Source | Purpose |
|---|---|
| Electric Vehicle Council | Australian EV market data and industry insights |
| Australian Renewable Energy Agency (ARENA) | Commercial fleet and charging infrastructure projects |
| Department of Climate Change, Energy, the Environment and Water (DCCEEW) | National EV policy and guidance |
| National Electric Vehicle Strategy | Australian Government EV policy framework |
| Energy Networks Australia | Electricity network and EV integration guidance |
| AS/NZS 3000 Wiring Rules | Electrical installation requirements |
| AS/NZS 3008 | Electrical cable selection and installation |
| AS/NZS 4777 (where applicable) | Integration of distributed energy resources |